CDA Reviews Uplift Work In Sector I-15

CDA reviews uplift work in three sub-sectors of I-15

Islamabad: A meeting was held here with the chairman of the Capital Development Authority (CDA) on development work in three subsectors of the I-15.

The meeting reviewed ongoing development work in Sector I-15, while Member Engineering provided a detailed report at the meeting that work in Sectors 1, 3, and 4 was progressing in full swing and would be completed in the coming years. months.

He said work is underway to provide all basic services in this area. Work on the underground roads is also proceeding rapidly, while the rest of the work is also proceeding rapidly.

Sector I-15

Also, Read 

Rawalpindi Ring Road New Alignment Begins

The works will be completed in the coming months, while the construction of underground and overhead tanks has also begun. Construction work on the Klot and the bridge are also underway. 

The clutches will also be completed in the next three months, while the bridge will also be completed in six months. The ongoing development work on I-15 will be completed within the allotted time.

In all parts of sub-sector I-15/3, the assignments will be assigned before the scheduled time in July and August 2021, while the scheduled time was July 2022.

The Capital Development Authority is also working on roads, sewers, bridges, air tanks, underground tanks, water supply, drainage and other sectors at the same time. Therefore, all development work will be completed on time.

Also, Read 

Amazon Business Centre Declared Software Technology Park

You can provide us with your feedback at hello@landster.pk and follow Landster Blogs for updates on the real estate sector of Pakistan.

Join The Discussion

Compare listings

Compare